This is an informational page for the rock slide that occurred on the Stillwater River Road. All updated on the slide, all remediation information, and any other pertinent information will be posted on this page.
Important Info and UPDATES from the County Rock Slide Team
- September 12, 2018 Project is complete and the road is open
- September 4, 2018 (PDF)
- May 22, 2018 (PDF) *Road Closure
- August 16, 2017 (PDF) * Road OPEN
- July 26, 2017 (PDF) *Work Starts 7/27/2017
- June 22, 2017 (PDF) *Preliminary Schedule
- June 8, 2017 (PDF)
- April 3, 2017 (PDF)
- March 2, 2017 (PDF) *Postponement Due to Weather
- January 11, 2017 (PDF)
- January 4, 2017 (PDF)
- July 29, 2016 (PDF) *Phase 3 Proposal Clarification
- July 28, 2016 (PDF)
- June 21, 2016 (PDF)
- April 18, 2016 (PDF)
- March 16, 2016 (PDF)
- March 14, 2016 (PDF)
- November 30, 2015 (PDF)
- October 7, 2015 (PDF)
- September 15, 2015 (PDF)
- August 21, 2015 (PDF)
Other reports and letters regarding the rock slide
- Shannon & Wilson, Inc Proposal Phase 3 Design Services – July 19, 2016 (PDF)
- Shannon & Wilson, Inc Proposal for Phase 2 Engineering Services – February 12, 2016 (PDF)
- Shannon & Wilson, Inc. Proposal for Rockslope Stabilization Engineering Services-November 30, 2015 (PDF)
- Geologic Setting of the Stillwater River Rockfall-September 18, 2015 (PDF)
- Fish & Wildlife Service-August 20, 2015 (Comment on Proposed Mitigation) (PDF)
- Geostabilization International –August 21, 2015 (Hazard Summary) (PDF)
- Corps of Army Engineers –August 21, 2015 (Receipt of Proposed Mitigation Request) (PDF)
- GeoStablilization International – July 13, 2015 (Preliminary Proposal) (PDF)
- SK Geotechnical – June 15, 2015 (Geotechnical Reconnaissance Report) (PDF)